‘A meaningful risk’: Oracle’s massive 1.3 GW Wisconsin AI campus faces severe power delays as grid review restarts — pushing customer delivery past 2027
Regulators withdrew their completeness finding on ATC's application after 564 changes were filed, delaying grid power to Oracle's Wisconsin AI campus.